Good day, Mission Support,

Date: 06APR2016 at 7:53 PM
Crew Engineer Name: Jonathan Beechner

Diesel – 50%
Propane – 35%
Gasoline (5 Gallon containers for ATV) –  1 full container, 1 half full container

Water (trailer) measured in cm from the bottom –  NA
Water (static) measured in cm from the bottom – 24.5in / 42in
Trailer to Static Pump used – Yes
Water (loft) – 47 gallons
Static to Loft Pump used – 64 gallons
Water Meter: 107263,1 gallons

Summary of Engineering activities: Routine check, filled ATV’s 1, 2, and 3 with gas. D. G. came and took the trailer. I emptied the tank before he left. He also took the diesel container and left another container of gas.
Questions and Concerns to Mission Support: No
Power: No word from Shannon today. Presumably still on cat.

Jonathan Beechner
Crew Engineer